Decommissioning Challenges and Practical Solutions for Gulf of America Subsea Tiebacks
Date & Time
Wednesday, February 17, 2027, 2:00 PM - 2:30 PM
Yohanna Ruocco
Description


Murphy’s decommissioning of four deepwater Gulf of America fields applied innovative engineering and execution strategies to address legacy liabilities and complex infrastructure, including recovery of a pipe-in-pipe flowline in 6,900 ft water depth, the first-in-industry application of rigid coiled tubing for flexible pipe, and recovery of more than 25 miles of umbilicals. This presentation will share key lessons learned in flowline cleanout, umbilical recovery, vessel selection, and regulatory engagement to reduce risk and improve execution certainty.
 